The scope of the current project is impressive, involving a total of 9 tanks, including 4 iso-tanks, 1 fire retardant tank, 4 polyol reserve tanks, and 1 pump station for fire retardants. The upcoming tasks encompass not only the installation of the tanks but also the relocation of a catalyst and the integration of iso-tanks and fire retardant tanks into the existing pipelines. We gladly embrace this challenge to ensure that the facilities operate smoothly and meet Recticel's requirements.
The assembly is scheduled to start in May 2024 at the Wevelgem location in Belgium.
We express our sincere gratitude and look forward to another successful collaboration.